on 2023 Nov 21 9:57 AM
We have production areas in our production where we produce contract orders with a quantity of 1. These must be produced and delivered within 5 days.
Scheduling is not necessary because we produce in sequential order. Therefore, planning in SAP REO is not desired. These are 500 orders per day. We would like to exlude these orders from planning in Reo.
As a selection parameter we can use the resource or the order type. The order type is saved in a customer field. Does anyone have a solution for that ?
Request clarification before answering.
Hi Manoel,
thank you, i will do that.
regards,
Andreas