SAP PPM: Phase number is incorrect when project is created using project template.

0 Kudos
234

When a project structure is created in cProject using project template, phase number is copied from project template phases. Which makes all the phases to have number equal to project template phase number. So if there are 10 projects created from template, there will be 10 phases with same number (DPR_TV_PHASE_ID). Is there a standard way to use standard number range DPR_EXTID (object type PO)?

How can we restrict fields copied from project template phase to operative project phase?

View Entire Topic
Brendan_Ward
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello Mahendra,

Please code BAdI DPR_ATTRIBUTES method SET_DEFAULTS_UPON_COPYING as described in KBA 2684810.

Regards,

Brendan