on 2024 Aug 13 9:20 AM
Hello experts,
we are using Order POD with EWM single order staging integration. But from time to time we have to consume a Non BOM item in production. To update the BOM in ERP is not an option, since the decission for those unplanned consumptions in made during running production.
I tried to add the component in the BOM in DM only (worked fine) and with EWM we made an Ad-hoc stock transfer to a production storage place. In DM I can consume the production stock but not in EWM with the error message that the component is not part of the PMR. Do you know how to trigger from DM a consumption of a Non BOM component in EWM?