on 2018 Feb 20 4:23 PM
Hello friends,
In my project we have automated creation of PS project through PPM Operation project once we create the project.
Now creating Task just below project definition creates WBS in PS project, we are not able to delete this as by this time it is already transferred.
My questions are
How we can restrict the user to create task just below Project definition in PPM Operational project?
Would also like to restrict the user to create the Phase manually as this copied directly from template?
Thanks in advance
Kailas