on 2019 Aug 07 11:40 AM
Hello All,
As per Latest Simplification list; SAP PS Claim Management will not be the target architecture , so SAP suggested to use the Project Issue and Change Management Functionality in S4HANA for PS.
But, If CPM is not in scope, how to use Stand Alone Project Issue and Change Management ( PICM ) function ??? Any workaround ??
As per my knowledge, we cant install PICM alone ( Atlist Project Workspace needs to map )
Experts advice require on that.
Thanks,
Akash Khandelwal
Request clarification before answering.
Without CPM or any other non standard tool. Using standard SAP PS, I did apply Project Version to map change order and it works.
In addition, CN41N report is one of powerful report that you can use to create and compare every Change Oder / Project Versions.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.