on 2017 May 29 6:49 AM
Hello,
We are trying to get PPM PS integration working.
This scenario can be split into two parts
1. Create portfolio item and use cProject template to create a cProject. - This is working.
2. Mark cProject as 'Flag for Transfer'/ 'Release', this should create a project in SAP PS. - We are facing issue in this part.
We have done required configuration for 'Multilevel Controlling - Accounting Integration' as per blog here. https://wiki.scn.sap.com/wiki/display/PLM/Multilevel+Controlling+-+Accounting+Integration+with+Proje...
Following is the error that we see on cProject Cockpit - COCPCPR
'Company Code is not defined'
We have checked multiple SCN pages for help and we think we have not missed a configuration. We doubt that we have done some configuration incorrectly. Can anybody help us on this?
Request clarification before answering.
Dear Mahendra,
Also check, if the business scenario is maintained in transaction IAOM4.
Please maintain the entry as follows:
Business Scenario Extens: CPROJECTS
Business Scenario: CPROJECTS
Sort: 1
Best regards,
Judith
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.