on 2017 May 29 6:49 AM
Hello,
We are trying to get PPM PS integration working.
This scenario can be split into two parts
1. Create portfolio item and use cProject template to create a cProject. - This is working.
2. Mark cProject as 'Flag for Transfer'/ 'Release', this should create a project in SAP PS. - We are facing issue in this part.
We have done required configuration for 'Multilevel Controlling - Accounting Integration' as per blog here. https://wiki.scn.sap.com/wiki/display/PLM/Multilevel+Controlling+-+Accounting+Integration+with+Proje...
Following is the error that we see on cProject Cockpit - COCPCPR
'Company Code is not defined'
We have checked multiple SCN pages for help and we think we have not missed a configuration. We doubt that we have done some configuration incorrectly. Can anybody help us on this?
Request clarification before answering.
Dear Mahendra,
Please check, if a company code is maintained in the PS-project-profile which is used for the creation of the PS-Project. You can do it by calling customizing transaction OPSA. (Tab: Organization)
Best regards,
Judith
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.