on 2015 May 07 3:05 PM
Hi Everyone,
After completing configuration setting require to add new Item type in portfolio, following message is coming when i am opening project in project management.. "Setting for Accounting Integration contain errors", I have done necessary configurations in activation of accounting integration, Still i am facing this issue, I would request experts to provide there inputs so that i can rectify this priority issue.
Regards
Gaurav Ahuja
Hi Francesco,
Thanks a lot, It seems issue resolved by running this
Need your more help pls..Now one issue coming while transfer of project to PS.
Error messge - error occurred when transferring in accounting ( dpr_fin_gecco024 ).
I created project profile by coping another. Is that something i am missing here. I would surely appreciate if you can help me in this priority issue.
Regards
Gaurav Ahuja
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Gaurav,
Anything which goes wrong on the ERP side (related to some missing/wrong customizing) could lead to this error message, so unfortunately there is no way to say what is wrong based just on the message itself.
Please proceed as suggested in the long text of error message DPR_FIN_GECCO024: access the Controlling Cockpit on the ERP system (transaction COCPCPR). Enter the relevant controlling area when prompted. Then find the error message(s) related to the object(s) for which creation via accounting integration has failed.
You should be able to post-process these error messages, this way you will hopefully get additional information concerning what exactly is causing the creation of these objects to fail (if not, then you may have to debug the post-processing and see where any why it is failing).
Best regards
Francesco