Hi,
We are in process of establishing process Downpayment with Resource related billing.
Requirement is Initially against project customer will provide the downpayment and when doing the billing with reference to resource consumption downpayment should get deducted and either debit or credit memo get issued.
I.e
VF01 Downpayment received 100,000 USD
1st month Actual cost consumption on project 50,000 USD
DP91 RRB execution – Cr Memo 50,000 USD (100,000-50,000)
2nd Month Actual cost consumption on project 90,000 USD
DP91 RRB Execution – Dr Memo 40,000 USD
We have gone through following notes for completing required configuration for given scenario.
858702 - Consulting note for resource-related down payments
858703 - Customizing for resource-related down payment
983961 - Customizing for resource-related down payment (2)
But we are not getting expected result when we are executing DP91. Only actual cost is coming as output and downpayment is not getting considered.
Is anyone gone through this scenario and getting any result ? Please provide if you any solution to achieve this process.