on 2014 Sep 25 5:00 PM
Hi DG experts,
I have setup DG schema to NOT (save online is not checked) let the user save the records if the check methods fails. This works well for the delivery. If a check method fails the user is unable to save the delivery.
I have assigned the same check schema to Shipments. For shipment the system is letting to save the shipment with a block? I need the shipment too to react the same way as it does for delivery to ensure that user cannot save the delivery until the DG errors are fixed.
Thanks
P.s
Request clarification before answering.
Dear P S
did you check: Dangerous Goods Checks in Shipment Documents - Dangerous Goods Management (EHS-DGP) - SAP Library
did you read SAP customizing help ?
C.B.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.