on 2011 May 16 6:45 PM
Hi,
We are on PPM5.0
We are currently working on cProjects-MSP client integration.
What we have not been able to configure for import/export so far is:
1. Task-Role-Resource assignment
Whereas we are are able to import/export the "Person Responsible" and "Role Responsible" fields, we have not been able to align the task-role-resource assignments.
We see a "Resource Name" column (Standard) in MSP. When we click on the drop down, we see all the roles from the cProjects project. But the alignment does not happen.
Summary:
On export and import, we need to automatically see the role-resource-task assignment. How is this possible?
2. Code field to "VC_BUPA_GUID" gets a number which is not the BP ID.
Is it possible to import the BP numbers in MSP. Also, how can we assign a number to the role in MSP such that on import into cProjects, the role is already staffed with the corresponding BP.
3. Is it possible to export all the resources (BPs) into a drop down in MSP - like we see the Project Type, Role Type etc.
Thanks.
Hi Deepak,
I think note 958210 will help you. Excerpt from the note
Resources attached to the Microsoft Project are transferred as Project Roles in cProjects. To create a Project Role in cProjects Project from Microsoft Project, it is necessary to mark a resource in Microsoft Project as Project Role with the Role Type.
There were many errors also in MSP export/import for roles. Notes 1454611, 1512363 solve some of the issues. Check for your version.
Regards,
Anuradha
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Anuradha,
Thanks for your inputs.
When we export to MSP, we see the cProjects roles under the "Resource Name" drop down in MSP.
However, they are only seen when we expand on the drop down.
For e.g. RoleA, and RoleB are two roles in cProjects project, along with many other roles.
Both of these roles are assigned to a task, say TASK1.
When exported to MSP, we expect both of these roles to show against TASKI, as "RoleA, RoleB" under the "Resource Name" column. However, these roles are not seen. They only appear as elements of drop down, along with all other roles in the project, when we explicitly click on the drop down.
Please let me know if I are missing out on something.
Thanks.