CADO Approved Manhours, and Confirmations Not Matching.

0 Kudos

I have a peculiar situation.

There are 1000 Approved Manhours reflecting in CADO Report.

After Running CAT5 for those 1000 Approved Manhours we see only 100 Confirmed.

The Rest 900 Approved Manhours must have gone to the Error Log due to some reason.

Hence, While We check COFC, and CN30, for the Network No, We do not find the remaining 900 Approved Manhours in the Error Logs.

On Repeated runs of CAT5, we still don't see any postings to the WBS. ( WBS is budgeted and Released to the Quantity of Manhours).

If the Approved Manhours are not being posted or not even considered post CAT5, and not even found in the Error Log, How is it possible then to

detect what the problem is with those unposted Approved Manhour Records.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Owais

Normally we do Confirmations either in Project builder CJ20N or single records confirmation in CN25. but there will be no chance of mismatching once they are approved in CAT4 if there is a proper activity type with Activity number with Network mapped in CAT2. Even when u post the data from CAT5 we get the complete list of approved/incorrect data report. Check the Network perfectly in project builder & run a record manually there before running in CATS & check them in AFRU table.. whether they tend to happen the similar or not.

Cheers

Pradyp

0 Kudos

We found out that there is a bug in the SAP Standard Program relating to CATS App.

SAP is releasing  OSS Notes relating to this problem. We are waiting to see how

these OSS Updates will help.

Regards,

Former Member
0 Kudos

Hi Owais

It will be gr8 if u can share the OSS updates released by SAP.

Cheers

Pradyp