on 2024 Oct 27 4:10 PM
Can we use peo instead of plm. Business currently using team Center. Can it be replaced by peo alone. can team centre be integrated with sap with peo or PLM
In what situation we use Plm and peo
is there similarities or differences
Request clarification before answering.
The short answer is No. You cannot use one or the other. Below is the explanation
With the above two points being clear, if someone is using an external PLM system (Like Siemens Teamcenter), then the master data from this PLM, like Change, Structures (aka BOMs), Parts (material master), Documents, etc., needs to be fed to downstream SAP S/4 for processing like MRP & Manufacturing for enrichment and actual usage. You will, therefore, need some (if not all) capabilities of SAP PLM (Like Change record & BOM) to bring into SAP S/4, which in turn will feed this master data in the form of version control master data to SAP PEO for actual manufacturing related activities like Bill of process (aka Routings) & Production orders. Refer attachment for a pictorial view.
I hope this answers your concern & gives some clarity. Feel free to reach out to me directly with any other product-related queries. Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
thanks much for laying out the scenario. So my link to the documentation should be what you are looking for. Here, the transfer of the data from Teamcenter to SAP is going automatically through Change Notices and related workflows to SAP S/4HANA. No manual intervention needed at all. Change Record and Change Master are being triggered automatically as part of the processing. These need to be used obviously. There is no "shortcut" to PEO within S/4HANA, as you need to govern the updates through change control.
Please let me know if this answers your inquiry.
Kind regards, Ulf.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for the reply.
The business (Aircraft) uses Siemens NX18 for CAD drawings, moves it to Siemens Teamcenter for BOM structure, and then creates the BOM materials in SAP (With ECN) by manually copying the data from Teamcenter. Also, ECNs are manually created and linked to products in SAP.
Now they would like to automate the process of manual copying and pasting of products from the Teamcenter to SAP with ECN. (Need mass creation of ECN and Mass Linkage of products to ECN). Also, they would like to opt for PEO.
Can we Use PEO alone instead of Siemens Teamcenter or SAP PLM for creating the BOM, Change Records?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.