Dear PS Experts,
I have a non-statistical project. Some of the WBSs defined under it are statistical and some are not. This is wrong. As you know, I cannot make this change for the current project/wbs.
When I want to create a new WBS in project, the statistical tick is automatically ticked and does not allow me to change it. I want to change it myself.
I wait help!
Request clarification before answering.
Check your PS configuration for the field status related to the Project Profile you are using. That is where fields can be set to Display only.