PS WBS Settings

0 Kudos
221

Dear PS Experts,

I have a non-statistical project. Some of the WBSs defined under it are statistical and some are not. This is wrong. As you know, I cannot make this change for the current project/wbs.

When I want to create a new WBS in project, the statistical tick is automatically ticked and does not allow me to change it. I want to change it myself.

I wait help!

View Entire Topic
Ken_Melching
Product and Topic Expert
Product and Topic Expert
0 Kudos

Check your PS configuration for the field status related to the Project Profile you are using.  That is where fields can be set to Display only.

0 Kudos
thank you answer @Ken_Melching .The project type used has not been assigned to the project profile No customization has been done. Could this be the reason?
Ken_Melching
Product and Topic Expert
Product and Topic Expert
0 Kudos
The "project type" is mostly for identification purposes and very little control functions. Please check with your SAP configuration expert to analyze your PS set-up.