Dear PS Experts,

I have a non-statistical project. Some of the WBSs defined under it are statistical and some are not. This is wrong. As you know, I cannot make this change for the current project/wbs.

When I want to create a new WBS in project, the statistical tick is automatically ticked and does not allow me to change it. I want to change it myself.

I wait help!

View Entire Topic
raymond_giuseppi
Active Contributor
0 Kudos

Start reading KBA 2441384 - Change WBS from statistical to non-statistical (which contains some links of interest)

0 Kudos

thanks your answer. but as i said,When I want to create a new wbs it comes in gray.