Hello BPC Experts,

I'm creating a BPC10 NW version demo environment for our prospect customer.

I made a data manager to import  BW data into BPC model from BW cube.

I need to import just one month data into BPC from the BW cube that has more than one month data.

When I run the data package manually, I can select a member of the time dimension prompt and I can import specific month data I want.

But, in a case where the program (data manager) runs by JOB monthly,

I can't select a member of the time dimension prompt manually.

So I want to know how to set a  variable value to the time dimension prompt from a system date etc. automatically.

Are there any way to set a variable value to the time dimension prompt on the data manager automatically from a system date?

Or, do you have any other solution to import just one month data into BPC from the BW cube that has more than one month data  by the data manager running on JOB ?

(without selecting a member of the time dimension prompt of the data package manually)

Thanks in advance,

Keisuke

Accepted Solutions (1)

Accepted Solutions (1)

former_member200327
Active Contributor
0 Kudos

Hi Keisuke,

There are multiple options of achieving this, but none of them straightforward.

1. Create a VirtualProvider on top of BW cube and put current month selection in inversion routine.

2. Create a file in UJFS and refer UJD_TEST_PACKAGE to it. Update that file once a month.

Regards,

Gersh

Former Member
0 Kudos

Hi Gersh

Sorry for my late reply and thanks for your helpful information.

I tried the second way of your information and I could configure it.  

And I 'll try first way of your information.


Regards,


Keisuke