How to get excact Budget planning value without exchange differences

patrick_g1
Active Participant
0 Kudos
195

Dear community,

our system has EUR as global standard currency but has a entity within CH and their currency CHF.

Problem now within SAP PS is how to get the exact budget for a project using CHF instead of EUR and its actual valuation compared to EUR?

We use TCode: S_ALR_87013558

We can change the display of the currency with this function:

patrick_g1_1-1736145777732.png

Disadvantage here is that the calculation of the value will be done based on the actual maintained currency valuation from EUR to CHF.

Is there a way to show the budget in CHF without any calculation from EUR to CHF?

thanks in advance. Best regards

Patrick

View Entire Topic
raymond_giuseppi
Active Contributor
0 Kudos

Basically each line item for budgeting is stored in the currency in which it was entered and in controlling area and object currencies. The exchange rates are calculated from the exchange rate type and the value date, this information comes from the  budget profile.

Did you customize the objects related to the CH entity in CHF, this would allow display in both currencies, object (CHF) and controllin area (EUR)