cancel
Showing results for 
Search instead for 
Did you mean: 

GRC Access Request (ARM) hold functionality and SLA

0 Kudos
622

Hi,

We noticed that due date for a GRC access request did not change if the request was put on hold. Is hold functionality will recalculate the due date based on configured SLA?

Thanks,

Adilah.

View Entire Topic
shivam_agarwal1
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi Adilah

No, due date will not be re-calculated when request is put on hold. This is as per the design.

Thanks

Shivam

0 Kudos

Hi Shivam,

Noted. Thanks for your response.

Adilah.