Hello, experts.

I'm looking for best practices for the following scenario: I have five different work centers to carry out a single operation. Whenever a production order is made, the quantity is distributed among those work centers based on capacity availability.

My customer requires work center-specific production confirmation reports, but I am unable to select or change the work center on the confirmation page because the field is greyed out.

How can we achieve this?

Accepted Solutions (0)

Answers (1)

Answers (1)

cindychen
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi , in this situation, you may consider to maintain different production versions with these different 5 work centers. And created production order according to the capacity load.

cindychen
Product and Topic Expert
Product and Topic Expert
0 Kudos
Or you just split the Operation into Multiple Suboperations, if you only create one production order