WM: mvt 261

Former Member
0 Kudos

Hi experts, when I did a notification for a process order (MM 261), parcial quantity from a big batch, WM move desired quantity to area 914. That's OK, but after creation of TO with LB12, WM move the rest of batch to Interim Area 914. So I have to move back to original area and storage bin. How come? How can I do the movement back?

Thanks

Rolando

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hello Rolando,

Use LT01 to create the transfer order with mvt type 999, moving from 914 st type to actual storage type.

Regards

Arif Mansuri

Answers (1)

Answers (1)

Former Member
0 Kudos

duff answer