on 2015 Jun 16 6:14 PM
I'm trying to find a trigger point where the Standard Cost Component Split is updated during cost estimate creation. I first debugged CK11N, and found nothing relating to the update of ckmkeph. I realized at this point, it may not update this until the release of the cost estimate. I went to debug CKME as well and still nothing. Does anyone else know of what transaction the CCS is actually updated?
I've researched the user exits for CK11N and none of those are relevant to my issue, so I was hoping to find the code myself to find a potential solution.
Thanks in advance.
Request clarification before answering.
Hi
Mat component comes from GBB-VBR
Sub-cont charges (if any) FRL key.
Source of Activity cost is routing
OHs component may come from costing Sheets.
Rajneesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
The 'exit' you mentioned is related with valuation methods I guess.
Can you please give more clarity on the requirement by giving example of that?
If suppose you want to move content which is related to materials, that is possible with use of material origin or by some other means also we may be able to force system to do so.
Regards
Rajneesh
User | Count |
---|---|
102 | |
39 | |
6 | |
5 | |
4 | |
3 | |
3 | |
2 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.