on 2011 Mar 03 10:08 AM
What's the difference between task list release for order and release for cost?
Pallavi,
The status of the task list determines in which other application areas the respective task list may be used.
Release for costing: means that the task list can be used to calculate costs in Transaction IA16 i.e. the costs for the task list operations would be calculated if released for costing status is set.
Release for use in the order: Released for Order means that you can use the task list in an order i.e. you could include operations from a task list in an order.
Regards,
Usman