WBS Planned Cost on Sales order

Former Member
0 Kudos

Hi Ajay and Experts,

We have created WBS element and assiged on Sales order line item in Account assigt tab (Accont ass cat M and Valuation M).

Is there any way to get the corresponding Planned cost of WBS on Sales order line item when WBS is assigned.

Thanks,

Sudha

Accepted Solutions (0)

Answers (1)

Answers (1)

ajaycwa1981
Active Contributor
0 Kudos

Hi

Assign the same BOM to SalesOrder and also the Costing VAriant... There is not other way in my opinion

br, Ajay M

Former Member
0 Kudos

Hi Ajay,

Can you please tell me on how we will assign BOM on sales order.

Thanks,

sudha

Former Member
0 Kudos

Hi,

Can you explain your scenario in detail? Why do you need to recognize planned cost of WBS element at sale order line item level?

Generally if we assign sale order line item to WBS element, we always recognize cost and revenue element at WBS level which we customize through OPSB.

Thanks,

Manoj

Former Member
0 Kudos

Hi Manoj,

We are in MTO Scenario but Production order we will settle to Mat itself

WBS assigning on sales order line item.

WBS we are using to capture any addtion cost towards paint etc.,

While calculating the Margin in Sales order we could able to get the Material cost through VPRS but towards the WBS planned cost is missing, so that the Margin is not coreect.

For this purpose we are planning to bring the WBS planned to to sales order to get the correct Margin.

Thanks,

sudha