Hello,

We are facing an issue when creating production orders manually through CO01 with configurable materials,when the material of the production order to be created does not correspond to the material of the sales order.

In this scenario system is not getting the configuration characteristics from the sales order but is getting them from the material, in MRP 3 view.

However if we run MRP the planned order created is getting the configuration characteristics from the sales order despite the materials are different.

Can you help us understand why this is happening?

Thank you

JGF

View Entire Topic
PDevhare
Newcomer
0 Kudos

How to fetch sales order classification into production order till sub-assembly level?

Answer :

Strategy groups

PDevhare_0-1718714733615.png

 

 

Strategy assignment with Reqmt type of Cust req

PDevhare_1-1718714733619.png

 

Strategy details

PDevhare_2-1718714733622.png

 

Requirements classes

PDevhare_3-1718714733624.png

 

PDevhare_4-1718714733630.png

 

Requirement Types

PDevhare_5-1718714733633.png

 

 

 

 

 

Account Assignment Categories

PDevhare_6-1718714733636.png

 

Strategy Z0 (MTS)

PDevhare_7-1718714733640.png

 

Strategy assignment with Reqs type of customer Reqmt

PDevhare_8-1718714733642.png

 

 

 

Strategy Z0 Details

PDevhare_9-1718714733646.png

 

Requirement Type assign to ReqCl

PDevhare_10-1718714733648.png

 

Requirement Classes

PDevhare_11-1718714733650.png

 

PDevhare_12-1718714733657.png

 

 

Master data

Also if you are using material type FERT & HALB then you have to activate the check box "Material configure"(Basic data 2) in FERT as well as HALB (sub-assembly) with the same master data.

And you have to create a "Configuration Profile for the Materials " using CU41 for both FERT & HALB.