on 2020 Sep 29 5:59 PM
Hi All,
We created a resource that have a defined capacity as 100 EA(See attached screenshot 1).
We have a fixed processing time on this resource but have to model variable capacity consumption based on the order qty.
Maintained the formula for processing in work center to get fixed duration, also i maintained formula in capacity to get the variable consumption.(See screenshot 2 and 3 attached)
Now i maintained the fixed duration setup time in the routing as 24 hr(See screenshot 4 attached) and transferred the PDS to PPDS. I can see that mode now has a fixed duration of 86400 Seconds(which is correct), but when i drill down and try to check the capacity requirement it is not update(See the screenshot 5 attached)
Due to this the multiple capacity are not consumed for the orders(see screenshot 6 for capacity utilization in DS board)
Thanks for the help
screenshot1.jpgscreenshot-2.jpgscreenshot-3.jpgscreenshot-4.jpgscreenshot-5.jpgscreenshot-6.jpg
Request clarification before answering.
Hi Neeraj,
This is Standard, if you need to populate the variable consumption through the PDS badi. The calculation needs to be written in the PDS badi. I understand you are trying to model a furnace kind of scenario.
Regards
Sasi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
120 | |
9 | |
8 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.