Hello experts,

i am in SAP 4.6c and i am having a problem with scale values on vendor rebates.

I have configured the system following the best practices of sap and setted an agreement based only on the vendor.

Everything seems to work fine except that when i execute MEB4 (create settlement via report) the system always get the first line of the value scale.

I am using the standard condition type A001.

Does anyone have a guess on what is wrong???

regards,

Diogo

Edited by: diogo dalessandro on Jan 4, 2008 10:33 AM

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

you must maintain the value scales for each period on the overview (mountain boutton)!