cancel
Showing results for 
Search instead for 
Did you mean: 

valuation class changes for open orders

Former Member
0 Kudos
44

what are the reason SAP doesn't recommend to change the Valuation class for open orders or when the material is in transit.

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi

SAP doesn't allow to change valuation class as through this system determine the valuation data( G/L account for which is to be posted).

and accordingly it calculates the MAP.

So it considers for that particular G/L the value and divide it by qty.

So if it allows to change valuation class ( means G/L) then it is not possible to determine correct valuation.

Regards,

Viijay

former_member192897
Active Contributor
0 Kudos

Hi,

System will not allow to change the Valuation classes of a Material in the Following cases:

1. Material Stock should be zero. If any stock is there it wont allow to change vc.

2. Material should not have any open Purchase Requisitions/ Purchase orders/ Reservations etc.

So, If if you want to change the Valuation class Transfer allthe stock of the material to another plant and delete all the related Transactions.

Reg,

Ashok

  • Assign points if useful.

former_member197616
Active Contributor
0 Kudos

Hi,

As you also know that valuation class plays the 'Key' role in valuating the material.(account determination)

due to that reason when ever the valution class of the material which is having a PO is tried to change system will not allow to change .