Hi Guys,

Validity start and end date in purchase order seems to be working fine in case we are doing service entry sheet wrt PO. When I do MIGO wrt PO's where dates are maintained , system does not give me error. Please suggest as to what message number should be activated so that I get error.

Regards,

SK

Accepted Solutions (1)

Accepted Solutions (1)

JL23
Active Contributor
0 Kudos

if you do not want a goods receipt beyond a certain date, then you should maintain a latest delivery date in the item detail delivery tab

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

This issue stands closed. I will go with "latest delivery date" in delivery tab at EKPO.

Thanks.

Regards,

SK

former_member183424
Active Contributor
0 Kudos

Okay...

Maintain the latest delivery date as same as validity end date...

And also maintain the message as error from OMCQ.

former_member183155
Active Contributor
0 Kudos

This message was moderated.

Former Member
0 Kudos

Hi,

Please clarify your problem, you mean to say when the dates are maintained the system should throw an error???

Sagnik

Former Member
0 Kudos

Hi,

Yes, Suppose if I enter  validity start and validity end date as 01.01.14  and 20.01.2014 in PO, and do MIGO on 30.01.2014, system should throw error..

Regards,

SK

former_member183424
Active Contributor
0 Kudos

Service acceptance doesn't depend on validity date ...

You can accept the service from ML81N whatever your validity is..

If you press F1 on validity start and validity end, then you can see the help.. Read that..

Former Member
0 Kudos

Hi Dev,

ML81N is being controlled via msg: SE 242 if the creation date is beyond date range in PO.

Regards,

SK

former_member183424
Active Contributor
0 Kudos

Yes.. You are right...

I have checked the scenario...

It works fine..

Then I hope you have found the option at yourself...

Just make the message as error..

Former Member
0 Kudos

Hi,

It is working for SES but not for MIGO. I want my MIGO to be controlled as per validity dates in PO's.

Regards,

SK

former_member183424
Active Contributor
0 Kudos

For service procurement..

I hope no need to do MIGO..

You can create SES and then you can accept SES from ML81N?

Anyway,

If you want to do this in MIGO stage, then you have to maintain the latest delivery date in PO and make the message as error "M7 - 163  Latest possible delivery date was &"