cancel
Showing results for 
Search instead for 
Did you mean: 

Using MD09 to pegging

Former Member
0 Kudos
143

Dear all.

I have some question for using MD09 to peg initial reservation.

I have 3 production order at the same day. Run MRP and the system will generate only one purchase requisition for 3 production order. I'm in progress by convert PR to PO, good receipt and complete PO. But when I use MD09 to peg from PO, the system said that that PO does not exist and I can't peg for this. What's wrong here or SAP does not support for pegging after PO be complete?

hope your reply

Thanks

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Did you input purcase order as well as purchase order line item number?.. it should allow you.

Former Member
0 Kudos

When i use MD09 and enter purchase number order after it be good receipt. the system inform one message is "no peg requirement exist"

the system does not allow for pegging after purchase order be good receipt.