on 2013 Mar 15 8:12 AM
Dear experts,
i have a user status... at wbs level
1. init- project creation
2. bugp-budget planning cj30 allowed only
3. bugr-budget release allowed only
4. exen- wbs release and other business transactions allowed.
and in opuu- under reservation/pur reservation field 2 is specified. i.e from release.
while creating project, while adding non stock material with code without code, in component overview if user select 3' (immediatly, in res/pur req field) by mistake then automatically a pr will get generated without wbs release and budget allocation/release.
in Init status....bus transaction mat pur req is already forbidden. however for only non stock material with mat code or without mat code in cj20n, while adding new mat if user select 3 it creates a pur req and allows to do po. but at the time of migo it prevents by another transactions.
So can anybody let me know in status init, which transaction i have to forbidden so that i can prevent raising pr /po at this juntion.
hope i am clear in my question
prashanth.
Request clarification before answering.
Dear Prashanth, hope you're well,
Were you able to find an answer for you question? I have the same problem in my system (user status forbids creating PR; but on CJ20N network the system allows the creation the PR nevertheless), and so far I couldnt find the thread that so well explains this issue like other members replied.
Thank you so much in advance.
Patricia Valentina.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
106 | |
39 | |
6 | |
5 | |
4 | |
3 | |
3 | |
2 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.