When trying to create material cost estimate with quantity structure in 6.0 ECC, it is giving a error as Costing item 00001 is not assigned to a cost component, what is to be done?

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

HI,

in ECC6.0 document spiliting is available on default. if u keep open that option, that will ask these types of assignments, u better deactivate doc spiliting option at co code level.

ramarao.p

Former Member
0 Kudos

Try to cost material 1 alone. It will give you the error message.

Check that error message. The message will tell you which cost element need to be assigned to cost component structure.

Then go to OKTZ and assign this to the reqd cost component structure

- Sandeep