on 2015 Nov 05 3:43 PM
Hi,
I need some help around work order user and system status. Requirement is after work order scheduling in MRS Planning board, We want system to set user status automatically. just to indicate that work order has been scheduled and need not be in planning board for next time.
Other need i think of how to set user status manually for the demand in planning board i saw option is there (select the demand and right click) but i guess i need to find a correct place to configure it.
Thanks,
Amit Kushwaha
Request clarification before answering.
Hi Amit
MRS Scheduling will change the system status and from the system status you want to trigger a user status. In order to do that use the configuration for the user status.
Select the user status which will be set by the system status and assign as highlighted below.
Now about MRS and on how to set the user status, I will try to find some screen shots/steps if I have some time.
Regards
Savas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
96 | |
39 | |
6 | |
5 | |
3 | |
3 | |
3 | |
2 | |
2 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.