Hello All,

I have just modified the Costing Data for 100 Work Centers CR02, setting a new "Activity Type" and "Activity Unit". But the Routing Data CA02 does not get updated correspondingly. I would like to ask is there any standard program which can help me to do the mass processing as to update the data to the corresponding routing?

Thanks.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Dear Jamison,

Yes

You can do it Via Work center by activating reference indicator tick

Or for mass you can go with CA85N

Regards

Madhu

Former Member
0 Kudos

Dear Experts,

I too have the same issue.

I am modifying the standard value in the parameter.

The parameter is already assigned to a standard value key and which is inturn assigned to work center.

Now any modification in parameter is not getting affected in routing even though reference indicator is maintained.

Is there any link with activity type maintained in costing tab under work center.

Regards,

Krishna

Anupam1143
Active Contributor
0 Kudos

HI

After changing the activity type in work center and activity units, select the reference indicator check box against each activity and then check in routing it will get updated automatically. Also refresh cost estimates after changing the activity types.

Check and revert

Regard

Anupam Sharma

sundaresan_velayudam
Active Contributor
0 Kudos

1) You can change as per Mr Anupam sharma Said

or

2) YOU can also Update the data IN CA85N

In selection criteria enter the respective work center and Plant

and In new Value Give

Same work center, Plant, activity value , Unit and activity type

execute

select the all the work center and then click mass change