Dear gurus,
i have a requirement whit the delivery date = 30.12.08 , and a PO whit the delivery date = 19.7.09.
After the run Mrp the system create a new RP and the PO don't considered .
if I modify the delivery date in 19.6.09 the system planned the PO.
These days are approximately 200 , where i can modify the range for planned the PO whit the delivery date after 19.7.09?
Are this values the parameters correct for my requirement?
I try in customizing whit the transaction OPPQ , and in the material master of the material in the view MPR 3 but the don't planned the PO.
Thanks a lot for cooperation .
Daniele Pistilli
PP TEAM
Check the planning horizon with respective and MRP group wise in t.code OMDX
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
90 | |
9 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.