Update planning horizon

Former Member
0 Kudos
129

Dear gurus,

i have a requirement whit the delivery date = 30.12.08 , and a PO whit the delivery date = 19.7.09.

After the run Mrp the system create a new RP and the PO don't considered .

if I modify the delivery date in 19.6.09 the system planned the PO.

These days are approximately 200 , where i can modify the range for planned the PO whit the delivery date after 19.7.09?

Are this values the parameters correct for my requirement?

I try in customizing whit the transaction OPPQ , and in the material master of the material in the view MPR 3 but the don't planned the PO.

Thanks a lot for cooperation .

Daniele Pistilli

PP TEAM

View Entire Topic
former_member207022
Active Contributor
0 Kudos

Check the planning horizon with respective and MRP group wise in t.code OMDX

Former Member
0 Kudos

Dear guris ,

i try set 999 in the flied Planning horizon for the MRP group but after run mrp the system non planned yet th PO whit the delivery date 21.7.09.

Are there outhers parameters to modify?

Thanks a lot

Daniele Pistilli

PP TEAM

Former Member
0 Kudos

Hi,

NO, it is not Planning horizon. Make changes in rescheduling horizon and read the suggestions carefully given previously.

Regards,

Dharma

Former Member
0 Kudos

Dear gurus ,

in the transaction OPPR the system planned the PO .

Thanks a lot for your help.

Daniele Pistilli