cancel
Showing results for 
Search instead for 
Did you mean: 

Update planning horizon

Former Member
0 Kudos
120

Dear gurus,

i have a requirement whit the delivery date = 30.12.08 , and a PO whit the delivery date = 19.7.09.

After the run Mrp the system create a new RP and the PO don't considered .

if I modify the delivery date in 19.6.09 the system planned the PO.

These days are approximately 200 , where i can modify the range for planned the PO whit the delivery date after 19.7.09?

Are this values the parameters correct for my requirement?

I try in customizing whit the transaction OPPQ , and in the material master of the material in the view MPR 3 but the don't planned the PO.

Thanks a lot for cooperation .

Daniele Pistilli

PP TEAM

Accepted Solutions (1)

Accepted Solutions (1)

former_member207022
Active Contributor
0 Kudos

Check the planning horizon with respective and MRP group wise in t.code OMDX

Former Member
0 Kudos

Dear guris ,

i try set 999 in the flied Planning horizon for the MRP group but after run mrp the system non planned yet th PO whit the delivery date 21.7.09.

Are there outhers parameters to modify?

Thanks a lot

Daniele Pistilli

PP TEAM

Former Member
0 Kudos

Hi,

NO, it is not Planning horizon. Make changes in rescheduling horizon and read the suggestions carefully given previously.

Regards,

Dharma

Former Member
0 Kudos

Dear gurus ,

in the transaction OPPR the system planned the PO .

Thanks a lot for your help.

Daniele Pistilli

PP TEAM

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Use tcode OPPQ, select rescheduling horizon. Change the rescheduling horizon days to max and check it. Now system will consider planned order.

If you assigned MRP group in material master, do changes in OPPR, it is higher priority.

Regards,

Dharma