on 2019 Oct 09 8:02 PM
Hi Expert,
We implemented counter base PM for PRT and measuring points are count upon production order confirmation (PRT assigned to PP order operation)
I have a scenario where I need to assign two PRTs (PRT1 & PRT2) into this operation and counters are updated evenly
(If the PP confirmation is done for 10 products PRT 1 counter 1 and PRT 2 counter 2 increase by 10 )
I need manually change the counter increasing quanty while doing the PP confimation eg: for counter 1 by 6 and for counter 2 by 4
Is this possible in standard CO11N screen?
Please help me with alternative
Thanks
Ashok
Request clarification before answering.
Hello,
The usage counter is updated in relation to the confirmed quantity for equipment PRTs that are assigned to the operation and for which a measuring point has been defined.
This mean, if the operation has an equipment PRT, assigned and this equipment PRT has a measuring point, then the confirmation will update the usage counter.
Regarding PRT usage formula you need to refer the standard SAPF02 formula so here you can create your own formula to update PRT counter with your own logic.
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.