Unknown Component in Subcon. Component in Purchase Request .

former_member223579
Participant
0 Kudos
71

Hi All,

I have an issue in subcontracting PR. When I check the subcontracting components in PR there is a entry of unknown component in the list.

say for example , In a BOM I could find 9 components but in PR list I could see 10 components.

No Manual entry was there .

Can anybody help to find ....

Thanks,

Siva.

Accepted Solutions (0)

Answers (1)

Answers (1)

Shubham1
Advisor
Advisor
0 Kudos

Hello

I think there is an issue during BOM explosion.

Any error messages encountered ?

I suggest you please go through the above document.

Regards

Shubham

former_member223579
Participant
0 Kudos

Hello,

No I didn't get any error message . Actually the process is,

MRP run->planned order -> PR->PO.

I can see the extra component in the SC list of PR which is not available in Material BOM.

as I said earlier it was  not entered manually .

is there any way to check what /When/Who changed in the Subcontracting component level.

can u please advise.

Thanks,

Siva.

JL23
Active Contributor
0 Kudos

Are you certain that you are checking the right BOM?

Are you certain that the BOM has not been changed since then?

Why are you certain that no manual adjustment was made to the BOM when creating the PR or PO?

Shubham1
Advisor
Advisor
0 Kudos

Hello

Go to AU10 T code  ,Press F9 and enter table name RSEB with start and end date of the change logs.