on 2013 Nov 21 8:43 AM
Hi,
Just Undo Status CLSD - then you can see Status TECO for the WBSE, then Undo Status TECO then you can see Status REL, before saving Check your AUC and go through all the tabs of AUC - may be somthing is missing at AUC level. thats why system is giving the message- correct it and then save project.
I have simulated same thing here but I did not get any such error.
Ideally this should not happen because when you were released WBSE at first time that time only you could have faced this issue - error while processing AUC.
still you can give a try.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Venkat,
I tried doing the same as you said but when i happen to save, i still get the same error.
I also simulated by creating project, posting cost and settling it to AUC then to FXA and undo the status to REL and it happens in my testing system.
Its just holding me up in production system, Not sure what/where i am missing.
Which parameter of AUC, You want me to check exactly & how ?
Thanks in advance !