Unable to add the component in the production order

prithzzz
Explorer
0 Kudos
385

Hello Experts,

I'm trying to add a component in the production order and getting an error. the component which I'm trying to add has the Base Unit of measure maintained as "M"-Meter in the material master but when I try to add this component in the production order the UOM is correctly getting determined as "M" but when I try to save the production order I'm getting the error "Unit of measure EA not allowed acc. to material master" - Message no. L0700. Can someone help me why this is blocking as I informed that component's Base UOM is "M" and also I have cross checked the material master the Alternate UOM relation is maintained for the "EA" and "M".

Thanks in advance for your feedback on this topic

View Entire Topic
1417064
Explorer
0 Kudos

Need both entries M = M & 2nd row M = EA.