on 2016 Mar 07 9:51 AM
Hello
We have a FERT process order that has a material in the BOM defined as a UoM of KG. We require the generated transfer requirement to display the UoM as G.
The base UoM is set as G. The unit of issue and the WM UoM are blank, so default to G as well. But it seems the transfer requirement is picking up the UoM from the process order/BOM.
How can I define it so the transfer requirement is generated with a different UoM or converts back to base UoM?
Thanks
Help others by sharing your knowledge.
AnswerRequest clarification before answering.
What value is in the field "Proposed UoM frm mat" in your WM1 view?