Transfer Estimated cost or planned cost in maintenance order as Project budget

Former Member
0 Kudos

Dear PM Expert,

can i convert estimated cost or planned cost from maintenance order as project (WBS) budget ?

Regards,

Karya

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

we cant transfer in standard SAP....only actual cost will transfer from main order to WBS if acc
assignment is WBS in order.

Please check Enhancement        IWO10010-Maint. order: Cust. enhancement for determining WBS element for this or you can take help from abap and debug in order during saving find out which badi or exit is triggered with CL_EXITHANDLER.

Regards

Vivek Patil

MTerence
Active Contributor
0 Kudos
Former Member
0 Kudos

Hi,

Please check below thread

Regards

Vivek Patil.

Former Member
0 Kudos

Hi Vivek,

my case is like this.

i have 1 maintenance order with total estimated cost = 10.000

and 1 have 1 WBS A, can 1 transfer my estimated cost 10.000 as WBS A project budget ?

regards,

Karya