I am looking for a user exit o BADI in the transaction CM21. Planning table.

The problem I would like to resolve is the following:

After finishing the scheduled process in this transaction I would like to change the storage location at component level in the order according to the production version selected. I need to do this because the good issue of the component need to be done from different storage location, I am identifying the storage location using different production version ( Alternative BOM).

Thank you in advance.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

CM21 is used to do the capacity levelling in the work center. But what way the storage location and the work center will link in your process.

Regards,