Hello,

How can I group all the materials that meet the criteria set in total planning (trans. MDBT) to show up in one purchase requisition instead of creating single item documents?

Thanks!

Märten Tootmaa

Accepted Solutions (1)

Accepted Solutions (1)

former_member184655
Active Contributor
0 Kudos

Dear Marten,

It's not possible to create a single purchase req document for all the materials req during MRP run through MDBT.

Regards

Mangalraj.S

Answers (2)

Answers (2)

Former Member
0 Kudos

How is it possible then?

I would probably need to program this process a bit.

Märten Tootmaa

former_member184655
Active Contributor
0 Kudos

Dear Marten,

It's not possible to create a single purchase req document for all the materials req during MRP run through MDBT.

Regards