The plant is changed from PR to PO

former_member259132
Participant
0 Kudos
543

Hi all, I created a PR for plant 1 and a cost center.

I try to create a PO from that PR by using ME21N and pulling PR from Document overview.

System changes the plant from Plant 1 to Plant 2 and displays a warning message

Purchase requisition xxxxxxxx, item 1 has a different plant, Message no. 06057

Any idea?

Thank you.

View Entire Topic
ajitkumar
Active Contributor
0 Kudos

Is this happening to you only or for all users? pl check in PO personal settings default values PO item whether a plant is mentioned here and always propose is check marked. .If so you may remove data from here if there is and try.

Else pl see whether any of the enhancement is inadvertently causing this.