The dependent requirement sequence in the stock requirement list / MRP list

Former Member
0 Kudos

Hello all,

When we view the stock requirement list ( MD04 ) or MRP list ( MD05) for a component, for sure we will see the dependent requirement as the "DEMAND" reflected in our MRP element .

Assume this component is a commom part for a few assemblies. If we come to a scenario that we have a few dependent requirements happened with different qty but with the same date, does anyone has any idea how the dependent requirements will be sorted in our MD04 and MD05 for that particular component that i look into now?

Example :-

I m looking at the MD04 for Component A

And i know there are a few dependent requirements

Assembly A - 100pcs on 01/01/2010

Assembly B - 200pcs on 01/01/2010

Assembly C - 300pcs on 01/01/2010

So, which of the dependent reuirement will be displayed as the top line in our MD04?

Appreciate if anyone can provide me some guidance.

Edited by: SiewMee on Nov 16, 2009 6:05 PM

Accepted Solutions (0)

Answers (1)

Answers (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Dependent requirements is displayed as per the BOM components of header material.

You can see all the dependant requirements in MD04 by clicking the tab SHOW OVERVIEW TREE. Even after that also it is not showing click the icon 'set up order structure' icon which is near to the date field.

Also you have option for filter as per reqt date also.

Please check this thread for details,

Regards,

R>brahmankar

Former Member
0 Kudos

Hello, thanks for your response.

Actually my question how is SAP sorting DepReq if multiple Dependent Requirement have same Due Date in the MD04?

I have found the answer. It is sorted according to the MRP element number from the table MDTB.