I got two order for same material and same BOM, but one of the order, material quantity: component quantity is 1:1,another is 2:1,why this happen?

View Entire Topic
P2003523347
Participant
0 Kudos

Hello Zhou,

Thanks for information.

Order header Qty is automatically recalculated based on Planned order for Production order10457566- 12,096 and Sales order for Production order10457565-17,280

Here Issue is during Production order header Qty calculation.so Here in CO08 Sales order Qty is conversion is 1:2 ratio. that part should check

Thanks

Best regards

Sunil Patil

cheng_zhou
Explorer
0 Kudos

but the wrong order is 10457566 which created by co40,and the plan order qty is 38,016.