Hi Experts,

I want to TECO automatically all the Maintenance Orders with status CONF via Job. Please how can I do this without DEV as I'm looking for standard way.

Thank you,

Regards,

Accepted Solutions (0)

Answers (3)

Answers (3)

Oscar_DC
Active Contributor
0 Kudos

I agree with Maria - as far as I know, there's no way to get this done in standard. There is a standard batch program to change the status from TECO to CLSD, but there's no standard program to go from CNF to TECO.

To credit Raheel. In advanced processes you have one person do the CNF and a different person do the TECO, but if the same person that is doing the CNF status is doing the TECO, then this is an extra-step.

YBS
Participant
0 Kudos

ok thank you Oscar !

MTerence
Active Contributor
0 Kudos

Hi Mike,

There is no standard solution available, unless you have a custom program to check whether the orders are CNF and then it should TECO the order.

Standard SAP provide opens options when to TECO. We need to customise based on our business requirement.

Regards

Terence

YBS
Participant
0 Kudos

ok thank you Maria !

RAHEEL_BABAR
Active Contributor
0 Kudos

Hi Mika,

Unfortunately, it is not recommended to TECO all maintenance orders with status CONF automatically via a job as this could cause unintended consequences and errors.

The TECO status is intended to indicate that the maintenance order is technically complete and no further processing is required. It is typically set manually by authorized personnel after reviewing the work order and ensuring all work has been completed and recorded correctly.

If you still want to proceed with automating TECO status, you can consider using standard SAP batch input programs to automate the process.

and you can also set Mass TECO status via IW38.

Regards

YBS
Participant
0 Kudos

Hi Raheel,

Thank you for your answer, I do agree with you but in my case it's not relevant that's why we want to close by Job.

Please could you give me more details about the Standard SAP batch input programs ?

Thank you for your help,