tcode for display of capacity utilization

Former Member
0 Kudos

Gurus,

can u please supply me with the t code for display of capacity utilization at all work centres at plant level. I also need scheduling reports.

Thanks

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

You can use standard reports like CM01, CM02......., CM25.

Hope this helps you.

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

In CM01 ,enter work center and plant.click on standard overview.You get week wise(you can change settings as per your wish day wise/month wise also)requirements,available capacity ,capacity load and remaining available capacity.

select one period and click on capa details/ period .The report shows tha materials, scheduling dates and pegged requirement qty.

Regards,

Rajaram.K