Tasklist creation makes difference in 4.6c and ECC6.0

former_member1242340
Participant
0 Kudos
91

Hi Everyone,

Till now we were using SAP 4.6c version in that while creating a Tasklist we used to enter the Purchase Order under the Operations of Tasklist,

when we are trying to give same Purchase in ECC6 then it is giving an error as

Document not an outline agreement (please enter outl. agreement)

Why is difference in 4.6c and ECC6, and how to rectify the error.

Thanks & Regards,
Rajesh

View Entire Topic
peter_atkin
Active Contributor
0 Kudos

Rajesh,

What is the full message text including the message number?

Also have a look at OSS Note 1364820

PeteA

former_member1242340
Participant
0 Kudos

Hi,

The full message with number:

Document not an outline agreement (please enter outl. agreement)

Message no. 06540

peter_atkin
Active Contributor
0 Kudos

This issue relates to the above OSS Note.

PeteA