Table ZL (time processing) in payroll run

Former Member
0 Kudos

Dear Expert,

I have a question regarding processing time data (negative time) without time evaluation. So the time data processing included in payroll (sub schema time data processing). Even though table ZL is being processed but when the payroll run finish its process I cannot find result ZL in time cluster C2. I want to make a report based on this table. The question is how come i can take the result ZL if the situation as stated above?

Super Thanks,

Dave

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

I think that you could add the function EXPRT ' ' ZL to save the ZL table into B2

Best regards

Former Member
0 Kudos

Hi Federico,

I totally miss that part. Super thanks for your help.

Best Regards,

David